Skip to main content

DETOUR ALERT: Paseo del Bosque Trail Repaving Near Tingley Beach

Please follow all detour signage during construction.

The City of Albuquerque Parks & Recreation Department is beginning work on improvements to the Paseo del Bosque Trail near Tingley Beach and the intersection of Central Avenue and Tingley Drive. The work will involve repaving several short trail segments that have been uplifted by tree roots in order to provide a safe and enjoyable experience for all trail users.

Please see information below related to detours during the repaving work:

Phase 1 - Begins Monday, April 13
The trail to the North next to the Biopark will have a dirt path detour (orange). The parking lot will be closed for this phase, which is expected to take 3-5 days. Users can find parking in other locations near the Bosque, including parking on the north side of Central at Sunset.

2020 Bosque Repaving Phase 1

Phase 2 - Expected to begin around April 20
The trail under Central Ave will be closed for two weeks while the asphalt is replaced with brushed concrete.

The triangle shaped portion to the south of Central will take 3-5 days to complete. Users will detour using the cross walk at Central and Tingley. There will also be a small dirt detour to the east of the triangle work to the south.

Detours are in orange. Closures in red.

Map 2020 Bosque Repaving Phase 2

Phase 3 - Expected to begin once the triangle portion of Phase 2 is complete
Phase III includes repaving a portion of trail between the Tingley Beach train station and the bike memorial. Users will be directed to detour onto the YCC dirt trail within the Bosque Open Space. This portion should take 5 days, likely Monday - Friday.

Phase 3A:Map 2020 Bosque Repaving Phase 3a

Phase 3B:
Map 2020 Bosque Repaving Phase 3b

Phase 3C:
Map 2020 Bosque Repaving Phase 3c