10-26-2016 - 17-302 - Strategic Review - Albuquerque International Sunport Terminal Restroom Remodel & Change Order No. 1
Change orders to construction contracts are not uncommon. Since 2013, change orders for the Aviation Department’s construction projects, increased the average total project cost by 4.4 percent. Change order No. 1 of the AIS Terminal Restroom Remodeling Project exceeded the average and was an 82 percent increase of the original project value.
https://www.cabq.gov/audit/news/10-26-2016-17-302-strategic-review-albuquerque-international-sunport-terminal-restroom-remodel-change-order-no-1
https://www.cabq.gov/++resource++plone-logo.svg
10-26-2016 - 17-302 - Strategic Review - Albuquerque International Sunport Terminal Restroom Remodel & Change Order No. 1
Change orders to construction contracts are not uncommon. Since 2013, change orders for the Aviation Department’s construction projects, increased the average total project cost by 4.4 percent. Change order No. 1 of the AIS Terminal Restroom Remodeling Project exceeded the average and was an 82 percent increase of the original project value.
https://www.cabq.gov/audit/news/10-26-2016-17-302-strategic-review-albuquerque-international-sunport-terminal-restroom-remodel-change-order-no-1
https://www.cabq.gov/++resource++plone-logo.svg
10-26-2016 - 17-302 - Strategic Review - Albuquerque International Sunport Terminal Restroom Remodel & Change Order No. 1
Change orders to construction contracts are not uncommon. Since 2013, change orders for the Aviation Department’s construction projects, increased the average total project cost by 4.4 percent. Change order No. 1 of the AIS Terminal Restroom Remodeling Project exceeded the average and was an 82 percent increase of the original project value.