Application #1958-M2, Kairos Power Southwest
The applicant is requesting a modification to Permit #1958-M1-1AR. The applicant is requesting:
The installation of:
- Two (2) 18, 000 acfm Donaldson DFE 4-32 dust collectors
- One (1) carbonizing furnace,
- One (1) Pebble Development Laboratory (PDL)
- Three (3) engineering testing units,
- Seven (7) building exhaust vents
- One (1) 3 HP diesel-fired emergency fire pump
Replacement of:
- One (1) 183 HP John Deere diesel-fired emergency fire pump with one (1) 422 HP diesel-fired emergency fire pump
Modification of:
- One (1) 900 HP Caterpillar diesel-fired emergency generator
- Four (4) 1490 HP Cummins diesel-fired emergency generators
Important Dates:
Comment Period Start Date: January 17, 2025
Comment Period End Date: February 17, 2025
Decision Due Date: April 13, 2025
Related Documents