scp-photo

Black Rock Services HP-2, northwest corner of the intersection of Carmony Lane NE and Alexander Boulevard NE, Albuquerque, New Mexico 87107

Black Rock Services, LLC requests a new air quality permit in Application #3443

Black Rock Services, LLC is requesting a new construction permit to install a 400-ton-per-hour (tph) hot mix asphalt (HMA) plant with a maximum production of 1,450,000 tons per year.  The HMA plant normal operating hours are from 6am to 5pm, five days per week, 45 weeks per year.  The maximum operating hours will be 24 hours per day between March and September; from 5am to 10pm in the months of February, October and November; and only daylight hours during the months of January and December.  The facility will consist of the following:

  1. Five cold aggregate storage piles; 
  2. One Recycled Asphalt Pavement (RAP) storage pile; 
  3. Five cold aggregate feed bins;
  4. One cold aggregate scalping screen; 
  5. Two RAP feed bins; 
  6. One RAP scalping screen; 
  7. One RAP crusher; 
  8. One mineral filler silo with baghouse;
  9. One drum dryer/mixer with baghouse;
  10. One asphalt drag conveyor;
  11. Multiple conveyors;
  12. Six asphalt storage silos;
  13. Three asphalt cement storage tanks; 
  14. One asphalt cement oil heater; and
  15. One Evotherm® tank.

 

Important Dates:

  • Comment Period Start Date:  December 8, 2021 
  • Comment End Date: January 7, 2022 
  • Decision Due Date: February 28, 2022

 

Related Documents: