Runway 4-22 & Taxiway A Reconstruction at DE II

Show Navigation
Latest From Twitter
 

Project Description:

 

DEII-Airport The existing Runway 4-22 at Double Eagle II Airport was constructed in the early 1980's and has reached the end of its design life. This project will reconstruct the existing runway and taxiway and replace runway and taxiway lighting, signage, and striping. The existing asphalt runway will be milled and recycled as base course with a new 4" asphalt runway placed.

Funding Category:

Aviation

aviationcounter

Program Name:

Airport Improvement Program

Project Funding Allocated:

$2,262,435

Total Spent:

$2,300,486 (as of 06/30/12)

Status:

Completed