New Singing Arrow Community Center

Project Contact

For more information or to comment on this project, please contact us.

Project Overview

For several years, Council Harris received requests for a new center for Singing Arrow residents. In 2013, the Councilor requested a Needs Assessment to identify gaps in services for the surrounding community. This analysis also determined that the preferred location for a new community center would be the North East end of Singing Arrow Park.

View updated information on Consensus Planning website.

Timeline of the Development of the Community Center

2013 | Needs Assessment completed (link below)
February 2016 | Parking lot purchased off of Wenonah Avenue
June 2016 | Archaeological study completed for the proposed area of the new center
June 2016 | Request for Proposals for design of center advertised
July 2016 | The Selection Advisory Committee received six proposals
August 2016 | Cherry/See/Reames Architects, PC is selected by the Selection Advisory Committee
September - November 2016 | EC-16-193, approving Cherry/See/Reames Architects, PC, is approved by the City Council and signed by the Mayor
January 2017 | An application for a conditional use was heard by the Zoning Hearing Examiner and approved
February 2017 | Public meetings begin to gather input on the design of the center
November 2017 | Site location undergoing hearing process

Funding

In 2011 and 2013, voters approved General Obligation Funds specific to the proposed community center. In 2015, voters approved the repurposing of Metropolitan Redevelopment Bond funding for the center. In addition, the State of New Mexico is also providing State Capital Outlay Funding.

Upcoming Public Meetings

No meetings scheduled at this time. Please check back. 