Frequently Asked Questions about the asbestos NESHAP (National Emission Standards For Hazardous Air Pollutants)

Asbestos Warning

The EPA has an Asbestos Ombudsman to provide information on the handling and abatement of asbestos in schools, the workplace and the home.

Also, the EPA Asbestos Ombudsman can help citizens with asbestos-in-school complaints.

The Ombudsman can be reached toll- free at (800) 368-5888.

Following our most common questions about NESHAP requirements and asbestos removal in Albuquerque.

Q: What Federal regulations apply to demolitions and renovations?

A: Code of Federal Regulations Title 40 Part 61 (National Emission Standards For Hazardous Air Pollutants, Subpart M (National Emission Standards for Asbestos) §61.145 Standard for demolition and renovation may apply.

Q: What is the purpose of the Asbestos National Emission Standards For Hazardous Air Pollutants (NESHAP) regulation?

A: The purpose is to protect the public health by minimizing the release of asbestos when facilities which contain Asbestos Containing Materials (ACMs) are demolished or renovated.

Q: Are there other local regulations that apply to demolitions or renovations?

A: Yes. Albuquerque-Bernalillo County Air Quality Regulation, 20.11.20.22 NMAC "DEMOLITION AND RENOVATION ACTIVITIES; FUGITIVE DUST CONTROL CONSTRUCTION PERMIT AND ASBESTOS NOTIFICATION REQUIREMENTS" may apply.

Q: What is the difference between demolishing a facility and renovating it?

A: "Demolition" and "renovation" are defined in the Federal Regulation. You "demolish" a facility when you remove or wreck any load-supporting structural member of that facility or perform any related operations; you also "demolish" a facility when you burn it. You "renovate" a facility when you alter any part of that facility in any other manner. Renovation includes stripping or removing asbestos from the facility.

Q: Who is responsible for enforcing the Asbestos NESHAP standards?

A: Under Section 112 of the Clean Air Act, Congress gave EPA the responsibility for enforcing regulations relating to asbestos renovations and demolitions. The CAA allows EPA to delegate this authority to State and local agencies. Even after EPA delegates responsibility to a State or local agency, EPA retains the authority to oversee agency performance and to enforce NESHAP regulations as appropriate.

Q: Are single-family private residences regulated by the Asbestos NESHAP or local regulation?

A: No. Both the federal and local regulation only regulate a residential building containing five or more dwellings, or a residential structure that will be demolished in order to build a nonresidential structure.

Q: How much asbestos must be present before the Asbestos NESHAP work practice standards apply to demolition projects?

A: Asbestos NESHAP regulations must be followed for demolitions of facilities with at least 80 linear meters (260 linear feet) of Regulated Asbestos Containing Materials (RACM) on pipes, 15 square meters (160 square feet) of RACM on other facility components, or at least one cubic meter (35 cubic feet) off facility components where the amount of RACM previously removed from pipes and other facility components could not be measured previously. However, all demolitions must notify the appropriate regulatory agency, even if no asbestos is present at the site, and all demolitions and renovations are "subject" to the Asbestos NESHAP in so far as owners and operators must determine if and how much asbestos is present at the site.

Q: What is a notification?

A: A notification is a written notice of intent to renovate or demolish. Notifications must contain certain specified information, including but not limited to, the scheduled starting and completion date of the work, the location of the site, the names of operators or asbestos removal contractors, methods of removal and the amount of asbestos, and whether the operation is a demolition or renovation. See Section 61.145(b) of the Asbestos NESHAP regulation.

Q: Who is responsible for submitting a notification - the owner of the building which is being demolished or renovated, or the contractor?

A: The NESHAP regulation states that either the owner of the building or operator of the demolition or renovation operation can submit the notification. Usually, the two parties decide together who will notify. If neither provide adequate notice, either or both parties may be held liable.

Q: Is there a form or format for notifications?

A: Yes, there is a suggested form for notifications.

Q: Do demolitions or renovations of buildings in which no asbestos is present require notification?

A: No. A notification is required when asbestos is present, and it is present at one of the following structures:

  1. Commercial building
  2. Residential building containing 5 or more dwellings or Residential structure that will be demolished in order to build a nonresidential structure or building.

If a notification is required, notification must be submitted pursuant to the applicable local or federal requirements.

Q: What is a "non-scheduled renovation operation"?

A: A "non-scheduled renovation operation" is a renovation operation that is caused by the routine failure of equipment which is expected to occur based on past operating experience, but for which an exact date cannot be predicted.

Q: Do I have to notify for non-scheduled operations? When?

A: Yes, if you can predict based on past experience that renovations will be necessary during the calendar year and the amount of RACM is likely to exceed the jurisdictional amount, notification is required. This notification must be submitted at least 10 working days before the end of the calendar year preceding the year for which notice is being given.

Note: Single renovation projects which exceed the threshold amount are not covered by this type of notice. A separate notification is required for these projects.

Q: Must I notify the agency again if I know that a specific renovation project involving more than the threshold amount (including the work covered by the calendar year notice for non- scheduled operations) is about to occur at a specific time?

A: Yes.

Q: Must I remove Category I non-friable material prior to demolition or renovation?

A: Under normal circumstances, Category I non-friable materials need not be removed prior to demolition or renovation, because generally these materials do not release significant amounts of asbestos fibers, even when damaged. This is not, however, a hard and fast rule. If Category I materials have become friable or are in poor condition, they must be removed. Also, if you sand, grind, abrade, drill, cut or chip any non-friable materials, including Category I materials, you must treat the material as friable, if more than the jurisdictional amount is involved.

Q: Does non-friable waste, if broken, damaged, etc., have to be wetted and contained?

A: Non-friable ACM that has been damaged during a demolition or renovation operation such that some portions of the material are crumbled, pulverized or reduced to powder is covered by the Asbestos NESHAP if the facility contains more than the threshold amount of RACM.

However, Category II non-friable ACM that has a high probability of being damaged by the demolition or renovation forces are expected to act on the materials such that it will be crumbled, pulverized, or reduced to powder, it must be removed prior to the demolition or renovation operation. It is the owner's or operator's responsibility to make these determinations.

Need Additional Help?